How to spot a technician coverage gap during an eye clinic session

Start with the work due in each block
I'd take one provider's morning session and mark the half hours where work needs to happen. Count the active minutes for workups, testing and any other duties already assigned. If a task can move, write down its earliest and latest workable times. If it spans two blocks, split the minutes across those blocks.
Then write down the technicians who are present and eligible for each task. Deduct breaks, training and commitments elsewhere. Give each technician one timeline. A person who can do both imaging and workups still has only 30 minutes in a half hour.
Check the busiest half hour
Here's a fictional 90-minute slice of a morning. Two technicians are scheduled throughout. One is eligible for the tests. The 40 workup minutes at 10:00 could come from four 10-minute workups. The 30 testing minutes could come from two 15-minute tests. The times are example inputs.
| Block | Workups | Tests | Available | Capacity after work |
|---|---|---|---|---|
| 9:30 AM | 25 | 15 | 60 | 20 remaining |
| 10:00 AM | 40 | 30 | 60 | 10 short |
| 10:30 AM | 25 | 15 | 60 | 20 remaining |
| Total | 90 | 60 | 180 | 30 remaining |
The slice has 30 minutes left overall. At 10:00, both tests use the full half hour of the eligible technician. That leaves 30 minutes for 40 minutes of workups. I'd move a 10-minute workup to 10:30 only if the visit can move with it and the receiving block still works. The 10:00 block would then have no margin. I'd check what happens if one test runs five minutes long.
A worksheet you can copy for any session
I'd start with the block that usually gets backed up. Copy these rows for that block and use local estimates. If there's a range, run the numbers once for the usual workload and again for a busier block. Keep the clinic's working copy with the people who own the schedule. The worksheet only needs task counts and minutes.
| What to write down | Your planning notes |
|---|---|
| Site, date and block | Site: _____ Date: _____ Time: _____ |
| Work due | For each task, record its count, minutes per task and the window it can be done in. Add the minutes due in this block: _____ |
| Technician time | Record each person's free minutes in the block after subtracting breaks, travel and other work. Add those minutes once: _____ |
| Where the work fits | Start with work that has the fewest eligible people or the tightest timing. Write each task on one eligible person's timeline. Check for overlapping tasks and flag minutes you couldn't place: _____ |
| Change and recheck | What will move? _____ Who will review it? _____ Which blocks or sites need another check? _____ |
Here's a second fictional example. Three people together have 60 free minutes in the block. There are 35 minutes of workups and 25 minutes of testing due. The only person eligible for the tests has 20 free minutes. I'd assign those 20 minutes to testing and use 35 of the other technicians' 40 minutes for workups. That leaves five minutes of workups capacity and five testing minutes I still can't place. I'd flag those five separately so the person fixing the schedule knows what kind of coverage to look for.
If you're estimating minutes from a schedule export, check what each EHR timestamp measures before putting it in the worksheet. When a change affects another team or site, use the schedule-change handoff to record who needs to confirm it.
Decide what to change before publishing
- Try moving flexible work within its allowed window. Recheck both blocks, including downstream room and provider availability.
- If the work can't move, check whether an eligible technician is free to help. Review the assignment they would leave before moving them.
- If neither change works, flag the block for the site lead. Adjust the template or coverage before approving it.
A glaucoma-clinic simulation study examined how demands on technicians varied in the clinic it studied. I use that as a reason to look at timing locally. The table here is a planning method with synthetic inputs. It doesn't predict waiting time or establish a safe staffing level.
Our workload forecasting guide explains how to estimate the work for a whole session. If the same device is the constraint, use the shared imaging guide to check its availability separately.
Sources and scope
- Discrete-event simulation in a glaucoma clinic (2019 conference proceedings)
In the clinic studied, the researchers examined technician demand by time and modeled bottlenecks. The study does not establish a staffing standard or validate this worksheet. Checked 2026-11-17.
- KRH: How technician forecasting and assignments work
KRH distinguishes session workload estimates, assignment constraints and human review. Checked 2026-11-17.